zaterdag 2 maart 2013

Some thoughts on QS, BIM and renderings

The past two months I have been busy making old fashioned quantity take-offs based on plans in dwg format and figures to be put in an excel file. 

The first project would be realised in a building team. So I could make sure that the quantity take-off would deliver knowledge for the developer, the designer and for the constructor. A hideous task but very rewarding. 

The following projects were more old fashioned school: projects in a design-bid-build setting with the sole purpose of checking the bill of quantities and gaining no other knowledge whatsoever. The contractor made a bid based on the quantity take-off delivered by the architect and considered it to be presumably. But, as it often goes in private projects, the negotiations tend towards a total fixed price so the quantities presumed at first need to be checked. 
That is where I pop in. The estimator is busy with his next "box" - cfr my first articles on this blog last year - and doesn't have the time to dig in the previous one. And another set of eyes detects other things. So they pay me to do the job.

The big difference with a decade ago is that there isn't any detailed quantity survey available to ease and shorten this time consuming control job. And skipping the control is no option because the rate of mistakes is no less than 10 years ago, quite on the contrary ... 

Why ?

The first problem is the marketing motto of BIM software: it will shorten the time needed on the drawing table. What they don't mention is the vast amount of extra time needed to put all the parameters right in order to get the thorough quantity take off needed to finetune the estimation to its lowest price. The second problem is the lack of knowledge about estimation of the person who makes the drawings.

Let me give you an example: the walls in a bathroom of an apartment and judge for yourself.

A lot of different situations for such a small room, isn't it ?

Next question: how are we going to deal with this given the still existing "design-bid-build" culture and the possibilities new software has to offer ?

Here is my point of view.

The designer really sticks to his core business and chooses the software who gives the best rendering possibilities in the shortest possible time. His output reaches no further than a "moodboard" so that every participant in the building process can get the "look and feel" of the project.

Than the engineers have a look at it and determine the width of the construction needed for stability and the insulation needed for thermic and acoustic comfort desired by the client.

BIM is primarily a database and should also be threated this way. It contains solely information of the engineers and contractors. Nice rendering possibilities remain in the "moodboard" software.
Yes, this means drawing everything twice but the second pair of eyes allows you to detect errors and opens up good old fashioned communication - sometimes people, in business, tend to forget that we can also use our mouth for speech instead of our fingers.

There are two possible ways to create this BIM depending on the knowledge of the person making the model.
  1. He/she knows how to estimate from a contractor's point of view. In this case everything of what is drawn in the example above is to be put into the model with the correct coding towards development, object and materials. A job as hideous as my excel file, believe me !
     
  2. He/she never worked as an estimator at a contractor company and therefore lacks the knowledge for thorough coding. In this case he/she makes sure that the parameters who generate the quantity take-off are left blank. This under the motto to put only these things into the model/database that are correct and generate knowledge for the other partners in the building process.
The person of situation 1 is currently a white raven and very hard to find. So most of the time we will be confronted with situation 2: a person who draws and is very familiar with BIM software and a person who estimates and hardly knows how to open a BIM file.

So, here is my advice when you choose a design-bid-build formula and work with BIM in the design phase:
  1. When you are not familiar with parameters in BIM, don't deliver the quantity take-off to the contractor. It only confuses him when he gets the wrong figures.
  2. Invite the contractor for a short briefing on how to use the BIM model in a BIM viewer software. Give him a locked BIM model to explore while estimating.
And remember: the purpose of BIM is not to save time but to eliminate errors by sharing a common tool. Only used at its best, it will ease the process. Carrelessly used it will generate extra failure and cost.

Kind regards,
Peggy
www.bouwdata.net 

donderdag 14 februari 2013

Bouwteams en overheidsopdrachten: hoe zou dit werken ?

Dat is wat Dimitri De Cock probeert uit te zoeken.

Dimitri De Cock werkt bij de Dienst Infrastructuur en Vastgoed van de provincie Antwerpen en volgt daarnaast de opleiding Master in the Real Estate aan de Antwerp Management School.
Vorig jaar gaf ik er een gastcollege omtrent construction management en geraakten we aan de praat over bouwteams en overheidsopdrachten. Waarom gaat het daar nog moeizamer dan in de privé sector ? Hij wijdt er zijn masterproef aan.

Het zou hem - en mij ! - enorm helpen, mocht u enkele minuten vrij maken om de enquête in te vullen op https://www.enquetesmaken.com/s/95fda47 

Van harte bedankt !

Vriendelijke groeten,
Peggy

vrijdag 21 december 2012

Merry Christmas and Happy New Year !

Dear readers,

it filled me with joy to see that my writings are appealing to readers all over the world: from Belgium to Malaysia and Brazil, from the US to Russia. I wish all of you a Merry Christmas and a Happy New Year !

Kind Regards,
Peggy

woensdag 5 december 2012

Explaining BouwData - part 8

Long time since I found time to write something on this blog. I still don't have a lot of time but sometimes one just has to create some :o)

Anyway, concerning BouwData: so far I explained the way the contractor looks at an estimation (material code) and the way the designer does (object code). As stated in one of my earliest writings on this blog, there is also a third party who has an interest in estimating: the owner or developper. For them there is the development code.

What is important to developpers ? m² floorspace ! 
And moreover: how many square meters is needed for construction ? And of the net floor space which remains, how much of it can be sold to clients in case of apartments or how much can be used for e.g. beds in a hospital ?

Again I looked for standards to help me out. In Belgium and the Netherlands we have a standard on how to measure surfaces : NBN B06-002 which is equal to the NEN 2630. The latter one is already replaced by the NEN 2580 when they defined the "Bouwbesluit". 
In Germany there is the DIN 277 and there is also an ISO 9836 available.

In 2011 the EN 15221-6 came to life but this is a standard for facility management. In the Netherlands a commission stated that this is an entirely different business, so they hold on to their NEN 2580. And in Belgium ... well, here it is business as usual: every organisation defines his own way of measuring :o)

What do I do ? The NBN B06-002 is quite simple and resembles a lot the NEN 2580, DIN 277 and ISO 9836. So I stick to that.

In this blog some practical guidelines in a nutshell.


Gross Floor Area
in Dutch: Bruto Vloeroppervlakte (BVO)
in DIN 277 indicated by BGF


According to the NBN B06-002 you have to count the gross floor area on all levels. Thus also the levels partially or entirely underground, technical levels, roof terraces and attics where you can do something. You measure along the outer side of the facade on each floor just above the floor finishing. 

Staircases, elevators and technical shafts, all belong to the BVO.

What doesn't belong to the BVO ?
  • smaller parts with a section < 0,5m² on the outside of the facade
  • free standing columns outside the facade with a section < 0,5m²
  • voides with a surface > 4m²
  • basements with a free height < 1,50m
  • roof surfaces who are not used as a terrace
  • open staircases outside the building
  • non covered area's such as patio's with a surface > 4m²
  • metallic gangways along the facade with maintenance as its single purpose
This is the same as in the DIN 277. 
In the ISO 9836 this is the "total floor area". This standard makes a distinction between spaces who are totally surrounded by walls and spaces who are partially open to the surrounding area. The NEN 2580 makes even a further distinction between covered outside spaces and non-covered outside spaces, both when adjacent to the building. We don't look at gardens or sitting areas which are detached from the building.

Personally I make the distinction by adding an "e" to BVO for exterior when I measure terrraces and balconies and adding an "i" for interior when measuring entirely closed rooms/buildings.

When your building has a common wall with its neighbour, you measure to the heartline of it.



Net Floor Area
in Dutch: Netto Vloeroppervlakte (NVO)
in DIN 277 indicated by NGF

In short the net floor area is the gross floor area minus solid construction elements.
Following items are to be left out of the measurement:
  • walls
    when you take all the walls out of the measurement, you speak of net floor area
    when you take only the bearing walls out, you speak of used floor area

    in Dutch the latter one is called "gebruiksoppervlakte" and marked by GO  
  • voides with a surface > 4m² 
  • parts of the room where the free height is < 1,5m
    remark: in the DIN 277 these parts do belong to the net floor area 
  • free standing column or a small wall when the groundsurface > 0,5m² 
  • shafts for technical ducts when the groundsurface > 0,5m²
Incidental alcoves on the outer walls with a groundsurface < 0,5m² are ignored.


Defined spaces and functions

In Belgium, every architect, creates names for the different spaces in a building. Sometimes he or she is consistent over all his/her projects, sometimes they like to invent names for every new project.

One could look at column 9 of table 0 of the SfB to define spaces but again, as with table 2 and 3 for the material code, I found the names in the Dutch "Bouwbesluit" more related to daily practice.

The DIN 277 roughly devides the net floor surface into:
  • usefull surface
  • technical spaces
  • spaces for traffic
  • rest surface (with the free height < 1,5m)
The Dutch "Bouwbesluit" is slightly different. 
They defined following spaces:

1 toilet
2 bathroom
3 technical spaces
4 spaces for traffic
5 storage of bicycles
6 storage of garbage
7 elevator shafts
8 space used by people
9 undefined space (is the same as the "rest surface" of the DIN 277)

Next to defined spaces they have defined functions for the use of spaces:

1 living
2 meeting
3 captivity
4 health
5 industry
6 office
7 lodging
8 education
9 sports
10 shopping
11 other functions where people are not constantly present



Development Code

So, how do I glue this and other questions concerning floor surfaces together into one code ?

When I receive a plan in a design & build project, I first check the terrein surface. Believe it or not but it happened that a part of the building was designed on the ground of the neighbour !

The total terrain surface (TO) can be devided into categories and is to be marked on a plan:
  • surface to be build on (BTO - red), measured according the NBN B06-002
  • surface to become a garden (ATO)
    this garden can be part of the community (ATO_C - yellow) or privately sold to one of the owners of the complex (ATO_P - blue)
  • surface left as it is (OTO - not coloured)


The next thing I check is the gross floor area (BVO) with a distinction between inside (BVOi - green) and outside (BVOe - purple) according to the rules mentioned above.



Then we get to the inside: the net floor area (NVO). 
Since the defined functions are only related to the defined space nr 8 "space where people remain", I use the code 8.01 for living, 8.02 for meeting, etc. 
In the category 8.11 I make further distinctions:

  • 8.11a garage
  • 8.11b storage 
  • 8.11c changing rooms
  • 8.11z other functions

Each room/function has again its own distinct color to use on plans. In this way I develop a visual "feeling":



For developers it is important to make a distinction between floor levels under the ground and floor levels above it. However, the standards don't give any answers when the soil isn't horizontal. The European Commission uses for his own buildings following method:



Level 0.00 on the outside of the facade is the level of the foothpad in the middel of the facade.
The floors who are situated between this outside level 0.00 and 1,50m below it, are considered "above groundlevel".
The Uniformat Classification uses A to mark the substructure en B to mark the superstructure and shell. In the development code I "borrow" this A and B.

Another important issue for developpers is to know the ratio between spaces used for the community and spaces to be sold to several owners. The first space I mark with a "C" and the latter with a "P".


An exemple of the Development Code: ACi8.11a

  • A : the space is to be found under groundlevel
    B is above groundlevel
     
  • C: the space is used by the whole community of owners
    P is space exclusively for a private owner
     
  • i: the space is completely surrounded by walls
    e is outer space adjacent to the facade
     
  • 8: space used by people
    see above for the other defined spaces
     
  • 11: other functions where people are not constantly present
    see above for the other defined functions
     
  • a: garage


Kind regards,
Peggy

zaterdag 27 oktober 2012

For beginners: how to determine a selling price ?

This is one for estimators at the beginning of their carreer and for those who are struggling with the calculations of their estimation software. Or, when you put it the other way around, how should your estimation software calculate ?

For the clients and architects who want to peep inside the kitchen of a general contractor: a warm welcome as well :o)

Here we go.

STEP 1

In a classic tender you have a list of articles where you have to put a price on.
Read carrefully the specifications and estimate the according costs for labor, material, equipment and subcontractors, article per article.
When finished the software will totalise this. These are the DIRECT COSTS.

STEP 2

As stated in my previous articles on this blog (and elsewhere), there are things you need in order to realise the building but which are not specifically mentioned in the tender.
Not estimating them will certainly result in a furious boss !
Some contractors estimate these costs in a seperate Excel file, some do this in the estimation software. It doesn't matter where you estimate it, as long as the job is done. 

The total sum of these costs are the INDIRECT COSTS.

Usually your boss wants to know how big these costs are related to the direct costs, preferably expressed in a percentage. How much this should be, really depends on what is specifically asked for in the tender: it can go from less than 1% when the architect wants to get a feeling with how a project is actually realised and mount up to 15% when it doesn't interest him at all.

STEP 1 and STEP 2 together is the PROJECT RELATED COST for the contractor.

In a formula:
                        project related cost = direct costs + indirect costs


STEP 3

A contractor has an office, an accountant and all other kinds of costs. 
And these costs remain whether he has a full order book or not. 
These are the GENERAL COSTS (in Dutch: algemene kosten or AK). Usually, these costs are taken into account bij adding a percentage on top of the production cost. 

In a formula:
                        total cost = project related cost x (1 + % general costs)

Some considerations:
  • Each contractor has a slightly different view on what is project related and what not.
    E.g. some contractors have a standard all risk insurance which is part of the general cost percentage; others look at the insurance project by project and add its cost to the project related cost.
  • Another thing: how big is the contractor you work for ? Does your company has his own engineering department ? In that case the general cost will be higher than the small contractor who only executes what is written down in the tender.

So, for you, as a beginning estimator, it is important to know what your boss exactly means by "general costs". Usually, the percentage is somewhere between 4% tot 8% of the project related cost.

STEP 1, 2 and 3 together is the TOTAL COST for the contractor.


STEP 4

A contractor wants / needs to make a profit. And your boss is not always so sure of the quality of your work. He will therefore add a percentage on the selling price for profit & risk. 

In a formula: 
                         selling price = total cost / (1 - percentage for profit & risk)

When you want to know how many euros or dollars this "dream" percentage for profit & risk is, the formula becomes:

                        profit & risk = selling price - total cost


STEP 5

Now we know what the total selling price will be, but how do we divide it over the articles of the tender ? Again, there are several considerations
  • Sometimes, clients indicate a fixed sum for certain articles.
    E.g. kitchens in apartment blocks. The final, individual owner of the apartment gets a fixed sum to buy the kitchen of his dreams (what happens when he wants to buy a more expensive or less expensive kitchen, I'll tell you in one of my next contributions to this blog). In these cases you're selling price is known and needs to be fixed .
    In the direct cost of that particular article you put 80% to 90% of the fixed sum depending on the general cost percentage you agree on with your client ànd the discount you expect to get from the subcontractor who actually will build the kitchen.

    When you make your estimation in Excel, add a column where you can add e.g. an asterix (*) to mark these prices.
      
  • Sometimes, the client already consulted subcontractors for e.g. windows.
    In other words, your client knows the price of the external joinery.

    Two remarks:

    1. When the client intends to work with a general contractor, he knows that the coördination of all the subcontractors come with a cost. In my experience clients are willing to pay from 3% up to 15% for it.

    2. As a general contractor you will get a better price of the subcontractor than your client because he is a one time client and you are a regular one.

    1. and 2. together means that you can put a selling price for these kind of items between 90% up to 110% of the direct cost of that particular article.

    Again, when you make your estimation in Excel, add e.g. an asterix (*) in the additional column to mark these prices.

Thus, the first thing you do after you have determined the total selling price, is to deal with the kind of articles mentioned above.

The total of these FIXED SELLING PRICES can be called SP1 (in Dutch VP1, verkoopprijs 1). 
The RELATED DIRECT COSTS need to be totalised as well and can be called DC1
(in Dutch KP1, kostprijs 1).


Secondly, you have to deal with the remaining articles.

The total sum of the REMAINING SELLING PRICES  can be called SP2. 
The total of the RELATED DIRECT COSTS can be called DC2.

The MULTIPLIER (in Dutch "overslag") of the direct costs in order to determine the individual selling prices of the remaining articles can be obtained by dividing the total of the remaining selling prices by the remaining direct costs.

In formulas: 
                         SP2 = selling price - SP1
                         DC2 = direct costs - DC1
                         multiplier = SP2 / DC2

As you can tell from above, the multiplier can have a wide range. When do you need to start worrying ? When the multiplier drops below 1,05 or exceeds 1,35. In those cases you better go and look for mistakes in your estimation :o)

Good news: for the time being, your job as an estimator is done.


STEP 6

It would be nice if the initial bid automatically results in a final contract. Perhaps this is the case in Utopia but certainly not in our daily construction world. Several times you will need to adjust you bid because of new quantities, new items, etc.

Before you make you're first adjustment, freeze all individual selling prices ! If you don't the formulas will start running their own life and you'll end up with different selling prices for articles where nothing changed. And trying to explain this to the client is an annoying thing to do and therefore is to be avoided at all times !
This also means that, in this phase of the selling process, you really need to keep your head cool.

There are several possibilities:
  • Only the quantity changes.
    In this case, you only need to adjust the related the direct cost but be aware.
    E.g. a pump to pour concrete will have no different cost if you pour that day a couple of m³ more or less. In other words, the selling price remains the same but the percentage of profit & risk might drop or increase.
    You could keep the same multiplier but all this small changes in individual selling prices of the tender will unnecessary complicate the sales process.
     
  • A new but similar article is added.
    In this case you need to apply the same multiplier as the one used with the existing simular articles. The selling price needs to be logical for the client !
     
  • A really new article is added.
    Here you have a choice in which multiplier you will use: the same as in the first bid or a different one. To make the choice you have to consider whether this new article has an influence on the indirect costs. It is also an opportunity to correct the dropping percentage of profit & risk due to only changing quantities or to correct a mistake you find in your estimation after handing over the bid to the client
What is important for your boss ? That is simple: how much money is left for profit & risk when the contract is signed ! And he will certainly compare this to the initial "dream" percentage which was set out in the first edition. So it is really important to keep a record of the changes you made throughout the sale process.

Not all that simple, but it surely is the most fun part of estimating !

Kind regards and keep warm this weekend !
Peggy






dinsdag 16 oktober 2012

Explaining BouwData - part 7

Before moving on, it is important to be sure that we all speak the same language. Especially for the interpretation of the NEN 2634 this is important. So here a little lexicon made by the university of Delft:

  • COMPLEX (same word can be used as well in Dutch as in English)
    This is a collection of buildings who are somehow related to one another
      
  • BOUWWERK or building in English
    This is the complete collection of functional and/or physical objects needed to give a solution to the need of housing (this can be a real house or a factory, hospital, school, etc. but not a road or bridge or solution for traffic)

    In the NEN 2634 the division of costs on this level is defined in table 6
    An exemple: 2 bouwkundige werken or, in English, constructional works
      
  • ELEMENTENCLUSTER or a cluster of elements in English
    This is a group of elements with related characteristics

    In the NEN 2634 the division of costs on this level is defined in table 7
    An exemple: 2A fundering or, in English, foundation
      
  • ELEMENT (same word can be used as well in Dutch as in English)
    This is a functional object with a specific purpose belonging to a building without being related to a specific physical solution.

    An element has a one-to-one relation to a building part

    In the NEN 2634 the division of costs on this level is defined in table 8
    An exemple: 2A.13 lagen op grond or, in English, layers on soil, explained as a layer designed to carry 3 t/m² and with a flatness of 5mm over a 2m length
      
  • BOUWDEEL or building part in English
    This is a physical object with a specific performance just because of the materials used and the way it is constructed.
    A building part has a one-to-one relation to a
    n element

    The layer on soil described as an element can also be described as a building part and it sounds like this: a layer on soil made out of 20cm concrete C25/30 with 25kg/m³ steel fibers on a PE foil of 0,2mm and layers of 5cm sand and 30cm of chippings
      
  • COMPONENT (same word can be used as well in Dutch as in English)
    These are the physical objects with a specific performance where building parts are made of.

    The NEN 2634 stops at the level of element but when you look beyond the summary of table 1 of SfB you find everywhere on the internet, you see something usefull.
    Especially when you look into the BB/SfB-plus which prof. Frank De Troyer from the University of Leuven published in 2008.
    An exemple: 2A.13.0 - demolition, excavation for layers on soil
      
  • ACTIVITEIT or activity in English
    This is a process of putting into work materials using labor and equipment

    Here, we enter back into the field of the material code and, as I wrote in one of my previous blogs, STABU is here much more usefull than the table 2 and 3 of SfB.
    One can say that the activities are the molecules of an estimation
      
  • MIDDEL or means in English
    This is a general information carrier for building materials, labor or equipment
    One can say that the means are the atoms of an estimation
Sounds interesting, doesn't it ? Certainly when you put it into a nice PPT slide:




I thought so as well when I started to put it into daily practice. 
It didn't take long to figger out that this was all too theoretical.
Let me give you an exemple: 2D.31 exterior wall openings. 
The idea is to have cost knowledge on a very rudimentary level when designing: a cost per square meter opening. This implicates that, when you want to put detailed estimations into a database, that you put the costs for big megadoors, ordinary windows and doors and automatic entrance doors all together in a big blender to generate the cost indicator of the exterior wall openings for that particular project.
So, I did. 
But I ended up spending a lot of time writing down what the result really meant and when I needed to use the database I always felt very insecure.

On top of that, when I looked at table 6, I felt I didn't have the means to make proper distinctions between the different mass studies I had in front of me.

I had to figger out something else.
And the answer was quite easy: move everything one phase up !
So, my nice PPT slide now looks like this:




I'm using it now for a couple of years and it never has let me down !

Kind regards,
Peggy
www.bouwdata.net 

maandag 15 oktober 2012

Explaining BouwData - part 6

First there was the sun with outdoor activities and then there were a lot of classic tenders to make a bid on. So, in the past month, my workplace resembled a lot my fancy old office filled with boxes full of paper. Luckily the paperwork was replaced by digital files. But there was another difference: although the projects where very different and for multiple clients, I always felt part of a team. So, to all of these clients: a warm thank you for achieving where my previous bosses failed !

But back to the future and BouwData now. 

The backbone of the different sets of agreements is the object code, a code with focus on function and life cycle cost. It can be used from the early consideration to invest in real estate to the phase of real cost engineering where knowledge about labor, material, equipment and subcontracting is necessary. It is from the object code that you can relate to the material code - the language of the contractor - and to the development code - the language of the developer.

It will take me some "parts" to explain its full depth, though.

The starting point was, as with the material code, the search for the standards to be used. And again the Netherlands proofed to be way ahead of Belgium.

On the highest, most general level, you have the same standard in Belgium and Holland: the NBN B06-003 / NEN 2631. This standard started his life in the Netherlands in 1979 and Belgium followed in 1983, 5 years later. Its focus is on investment costs and sums up, quite precisely, the kind of cost you need to consider :

  1. the acquisition of the ground you want to build on and the costs you have to make it ready for the contractor to plug in the socket and start building. Yes, this includes getting rid of trees, bushes and all kind of dirt, making sure that the groundwater has dropped sufficiently  if necesarry and that electricity and water is available on site.
    Why ? Well, these costs can have an influence on you're choice of spot you want to realise your project on, more or less regardless of the design
  2. the cost of the building itself including all equipment which is fixed to the building and not related to the production process which will occur when the building is in use.
    Important to notice: in this fairly old standard they already stated that there are different levels and ways to look at these costs: from the point of view from the developer (e.g. if you want to build a hospital, costs are in the earliest phase related to the number of beds), over the point of view from the designer (elements of the model), what you need when tendering to the point of view from the constructor (the sequence of coming to the building site).
  3. the cost of equipment related to the use of the building
  4. additional costs such as fees for designers, assurance, financing, moving into the building, etc.
Quite I good start and still accurate today but it is lacking detail.

In 2002, they realised this in the Netherlands as well. So they made the NEN 2634 which related the previous standard on investment costs to the international table 1 concerning elements of a new design of the SfB, the international classification system for construction. In this standard they define more precisely all phases of the design and building process and state how costs should be defined in every single one of them.

The object code is also the set of agreements to discuss Life Cycle Cost. 
The previous standards where made in a time where the world of design & construction had nothing to do with the world of facility management. In those days, nobody had ever heard of LCC. So I searched for standards in that world and yes, they also had felt the need of organising their costs. And again, the Netherlands proofed to be ahead of Belgium. They installed the NEN 2632 in 1980 and Belgium followed by taken it entirely over in 1983, calling it the NBN B06-004.

So, looking at all these standards I had sufficient background to relate it to my 15 years of estimating experience.

How ? Read the next part ! And I promise not to wait another month this time :o)

Kind regards.
Peggy